Deadman Creek Native Aquatic Species Restoration
Project ID: 4610
Status: Completed
Fiscal Year: 2019
Submitted By: 467
Project Manager: James DeRito
PM Agency: Trout Unlimited
PM Office: National Office
Lead: Trout Unlimited
WRI Region: Northern
Description:
Two outlet structures will be constructed to be full fish barriers on the existing lower pond on Deadman Creek. A spillway structure will be installed on the upper pond to prevent erosion and dam failure. Piscicide treatments will be used to remove non-native Brook Trout to protect and enhance populations of Bonneville Cutthroat Trout, Northern Leatherside Chub, and Boreal Toads in the ponds and about 3 miles of stream.
Location:
The project is located on Deadman Creek, a tributary of Mill Creek, which flows into the Bear River. The fish barrier will be located on an existing pond on the property of UintaLands in Summit County.
Project Need
Need For Project:
Brook Trout are present with BCT, NLC, and boreal toad in Deadman Creek. UDWR desires to remove the Brook Trout and have only native aquatic species present. A low dam and pond currently serves as a partial fish barrier and will be reconstructed to serve as a full fish barrier. In addition, the owners of the dam (Uintalands) desire to dredge the pond to improve the recreational fishery. The dam of the upper pond has eroded and a stable dam and spillway is desired.
Objectives:
1) Dewater and dredge the lower pond. 2) Install a riser outlet and auxiliary spillway on lower pond. 3) Construct a spillway on upper pond. 4) Complete renovation treatments to remove Brook Trout. 5) Return all native aquatic species back to creek.
Project Location/Timing Justification (Why Here? Why Now?):
Many cutthroat trout populations are lost because of Brook Trout expansion. If Brook Trout are not removed from places where they are present with BCT, then it's likely that the BCT population will be extirpated. Mill Creek and its tributary, Deadman Creek, are a genetically pure population of BCT. One of the main sources of Brook Trout in the drainage is Deadman Creek and this project will eradicate this source of Brook Trout above the constructed barrier. Brook Trout have similar effects on NLC; Deadman Creek is one of 3 extant populations remaining in Utah. In addition, one of six known Boreal Toad breeding locations in the Uinta Mountains exist in Deadman Creek; the eradication of this piscivorous fish would benefit this species. The willingness of Uintalands to allow the use of their dam as a full fish barrier is possible because they would like dredge the pond and improve the dam.
Relation To Management Plan:
Utah Wildlife Action Plan 2015: BCT and Boreal/Western Toad are both N4 species. Northern Leatherside Chub are an N3 species. All three species have listed as a High Threat: Invasive Wildlife Species - Non-native. This restoration project on Deadman Creek will address the removal of the non-native species (Brook Trout) to benefit all three species. UDWR Strategic Plan: this project will help the UDWR meet its Resource Goal, which is to "expand wildlife populations and conserve sensitive species by protecting and improving wildlife habitat. This project will specifically address objectives 2 and 3 of the UDWR Resource Goal, which are to (1) "increase fish and game populations to meet management plan objectives and expand quality fishing and hunting opportunities," and to (2) "conserve sensitive species to prevent them from becoming listed as threatened or endangered." UDWR Upper Bear River Management Plan (hydrologic unit 16010101): Identifies native and nonnative interactions as a resource and biological issue in this watershed [page 9]. Management strategies for BCT include (1) "chemical treatment of streams or lakes to remove nonnative fish" [page 11]. Management strategies for NLC include (2) "removal of nonnative fish species" and (3) "introduction into historical range" [page11]. Bonneville Cutthroat Trout Conservation Agreement and Strategy (signed by all states within historic range): The goal of the BCT CAS is to (1) "ensure the long-term existence of BCT within its historic range [page 2]. Specific actions include (2) the selective control of nonnative species [page 34, sections 4(a, b, and c)], as well as (3) subsequent introduction/re-introduction actions [page 35, sections 5(a, b and c). This project will also help to address the specific objective of additional BCT conservation populations in the Bear River in Utah [Table 2]. The UDWR and the USFWS completed a Utah Northern-region wide environmental assessment (2012) that covers the construction of fish barriers and conducting rotenone treatments. UDWR Rangewide Conservation Agreement and Strategy for Northern leatherside chub: The goal of this effort is to (1) "ensure the long-term persistence of northern leatherside chub within its historic range" by implementing strategies including to (2) "restore populations at selected localities within the historic range" [page 1]. Achievement of this goal requires implementation of conservation elements such as (3) nonnative control and (4) range expansion [pages 5 -- 6], which are proposed for Deadman Creek. Boreal Toad (Bufo boreas boreas) Conservation Plan.
Fire / Fuels:
Not applicable.
Water Quality/Quantity:
Not applicable.
Compliance:
Archaeology survey will be completed in-house by DWR. Included $2,000 in-kind for cultural resource inventory. No NEPA wil be required for the fish barrier on private property. The rotenone treatment is covered under the EA completed by the USFWS and UDWR in 2012.
Methods:
The lower pond dam will be notched to drain the pond. The creek will be temporarily piped around or through the pond area. The pond will be dredged and deepened by UintaLands. They have a bulldozer, backhoe, and access to a D8 for the dredging and dirt work. Useable fill will be placed on top of the dam or the road adjacent the pond. This will increase the freeboard of the dam from the current 1 foot to about 3 feet to protect theses structures from times of high flows. Dam materials must be placed and compacted to meet specifications. A geotechnical contractor will test materials and compaction before and during the dam reconstruction process. Dredged fill not meeting specifications for the dam or road will be spread on adjacent vegetated areas. A riser outlet structure will be installed in about the center of the dam. A concrete foundation will be poured for the structure. The riser and outlet pipe from it will be about 30" diameter and capable of passing a 50-year flow. Low density concrete will be poured along the outlet pipe to prevent water movement from the pond along this route. A gangway will be installed for access to operate and maintain the riser structure. An auxiliary spillway structure consisting of a concrete weir and apron leading to rock rubble will be installed in the northeast corner of the pond. A concrete spillway structure will be constructed on the upper pond to prevent dam erosion and failure. The UDWR will conduct the rotenone treatment on about 3 miles of fish bearing water upstream of the lower pond. Following the treatment, the lower pond will be filled. A second treatment will occur in 2020.
Monitoring:
Post-project: the UDWR will complete surveys of the ponds for Northern Leatherside Chubs (NLC) and Boreal Toads. Electrofishing of the stream length upstream of the ponds to the upstream extent of fish bearing water will also be completed to assess Brook Trout removal and BCT distribution. These surveys and monitoring efforts will be disseminated in UDWR's annual Northern Region aquatic monitoring reports. TU will monitor the fish barrier and outlets on the two ponds to assess passage of high stream flows and impassability to non-native fishes downstream.
Partners:
Utah Division of Wildlife Resources, UintaLands, Trout Unlimited, Uinta-Wasatch-Cache National Forest
Future Management:
Deadman Creek is currently managed by UDWR and the UWC for native fishes and Boreal Toads and will continue as such with this project. Monitoring for all three species is part of UDWR's regular aquatic monitoring program. Adaptive management will be implemented dependent upon findings of surveys and monitoring efforts.
Sustainable Uses of Natural Resources:
Not applicable.
Budget WRI/DWR Other Budget Total In-Kind Grand Total
$30,000.00 $112,047.00 $142,047.00 $30,921.00 $172,968.00
Item Description WRI Other In-Kind Year
Other USFS: planning and involvement with the treatment, coordination, outreach and education for forest users. $0.00 $0.00 $1,500.00 2021
Archaeological Clearance UDWR in-kind $0.00 $0.00 $2,500.00 2019
Materials and Supplies Initial purchase of construction supplies $0.00 $4,118.00 $0.00 2019
Contractual Services TU project planning, coordination with contractors (engineering and construction), coordination with partners, management of grants. $0.00 $0.00 $5,000.00 2020
Contractual Services TU grant management, coordination with construction contractor and Uintalands to drain pond for treatment, participation in rotenone treatment. $0.00 $0.00 $2,000.00 2021
Materials and Supplies Riser pipe and auxiliary spillways: 30" pipe riser, 30" outlet CMP, aluminum stop logs, gangway, concrete, rip rap $15,000.00 $67,166.00 $0.00 2020
Contractual Services Construction contractor: compaction of site, install of pipe riser and auxiliary spillways. WNTI in-kind for construction grant management. $15,000.00 $16,900.00 $1,500.00 2020
Other Excavation and dredging of lower pond, placement of useable dredge materials on dam and roadway, hauling and spreading of unusable dredge materials $0.00 $19,070.00 $9,921.00 2020
Contractual Services Geotechnical contractor inspection of soil compaction and soil testing for dams $0.00 $1,293.00 $0.00 2020
Contractual Services Construction oversight by engineering firm $0.00 $3,500.00 $0.00 2020
Contractual Services TU project planning, construction contractor bid tours and selection, coordination with landowners, stream permitting. $0.00 $0.00 $3,500.00 2019
Other UDWR planning and preparation for piscicide treatment, implementation, fish reintroduction. $0.00 $0.00 $5,000.00 2021
Funding WRI/DWR Other Funding Total In-Kind Grand Total
$30,000.00 $112,047.00 $142,047.00 $30,921.00 $172,968.00
Source Phase Description Amount Other In-Kind Year
Uintalands Association Cash towards construction contract. In-kind donation of 240 tons of gravel and hauling for dam and road rebuild adjacent and coordination with project partners. $0.00 $19,070.00 $9,921.00 2020
Utah Division of Wildlife Resources (UDWR) Archaeology clearance, planning and coordination with landowners and partners. $0.00 $0.00 $2,500.00 2019
Trout Unlimited Project planning, construction contractor bid tours and selection, coordination with landowners, stream permitting $0.00 $0.00 $3,500.00 2019
United States Forest Service (USFS) Materials purchase for dam rebuild (direct payments $15k) and through TU ($6,371) $0.00 $21,371.00 $0.00 2020
Western Native Trout Initiative (WNTI) WNTI secured construction funding for project through Fish America Foundation. In-kind for grant management and reporting. $0.00 $16,900.00 $1,500.00 2020
Habitat Council Account HCRF $30,000.00 $0.00 $0.00 2019
Species Protection Account Funding for construction materials and labor for the dam rebuild. $0.00 $4,118.00 $0.00 2019
Utah Division of Wildlife Resources (UDWR) Rotentone treating planning, implementation, fish reintroduction. $0.00 $0.00 $5,000.00 2020
Trout Unlimited Project planning, coordination with contractors (engineering and construction), coordination with partners, management of grants $0.00 $0.00 $5,000.00 2020
Trout Unlimited Grant management, coordination with construction contractor and Uintalands to drain pond for treatment, participation in rotenone treatment $0.00 $0.00 $2,000.00 2021
United States Forest Service (USFS) Planning and involvement with the treatment, coordination, outreach and education for forest users, etc $0.00 $0.00 $1,500.00 2021
Species Protection Account Purchase of construction materials. $0.00 $35,882.00 $0.00 2020
U.S. Fish and Wildlife Service (USFWS) Partners program funding for construction $0.00 $9,913.00 $0.00 2020
The Nature Conservancy (TNC) Engineering oversight ($3,500) and soil compaction testing ($1,293) $0.00 $4,793.00 $0.00 2020
Species
Species "N" Rank HIG/F Rank
Bonneville Cutthroat Trout N4 R1
Threat Impact
Invasive Wildlife Species - Non-native High
Northern Leatherside Chub N3
Threat Impact
Invasive Wildlife Species - Non-native Low
Western Toad N4
Threat Impact
Disease – Alien Organisms High
Western Toad N4
Threat Impact
Invasive Wildlife Species - Non-native Low
Habitats
Habitat
Aquatic-Forested
Threat Impact
Fire and Fire Suppression Low
Open Water
Threat Impact
Sediment Transport Imbalance Medium
Riverine
Threat Impact
Fire and Fire Suppression Medium
Project Comments
Comment 01/30/2018 Type: 1 Commenter: Jimi Gragg
Great project, you're probably under-selling its diverse benefits. My only direct suggestion would be to use the 2015-2025 WAP and not the expired, 2005-2015 version. The new version lists the threats to species and habitats, using the exact same terms available in the WRI database drop-down menus. Thank you.
Comment 02/07/2018 Type: 1 Commenter: James DeRito
Thanks Jimi. I adjusted the citation and reference to the 2015 - 2025 WAP. I used the exact terms of ranks and threat (non-native species) for all three native species: Bonneville Cutthroat Trout, Northern Leatherside Chub, and Boreal Toad.
Comment 01/31/2018 Type: 1 Commenter: Paul Thompson
This is a unique project that will have a direct benefit to three WAP species. The UDWR has worked hard to bring Uinta Lands on board with this project and work with UDWR, TU, and the USFS to continue to manage this watershed for native species. The sterile rainbow trout that Uinta Lands will be allowed to stock into the newly dredged/constructed pond will not detract from managing the watershed for native species.
Comment 09/08/2021 Type: 2 Commenter: Alison Whittaker
This comment has been deleted by author or admin.
Comment 09/08/2021 Type: 2 Commenter: Alison Whittaker
This comment has been deleted by author or admin.
Comment 09/08/2021 Type: 2 Commenter: Alison Whittaker
Please enter any missing expenses, highlighted in rust, on the Finance Page. When you have completed that please go back to the Completion Form and finalize your report again so I know that it has been completed. Thanks.
Comment 09/28/2021 Type: 2 Commenter: Alison Whittaker
Hey Jim - I need the missing expenses for this project as well for the legislature report. Please get them entered ASAP.
Comment 09/29/2021 Type: 2 Commenter: Alison Whittaker
Thanks for the quick response. I have moved it to completed.
Completion
Start Date:
07/01/2018
End Date:
09/21/2020
FY Implemented:
2021
Final Methods:
Project construction began on the dam rebuild and pond deepening during September 2019. The emergency spillway was completed during June 2020. The Utah Division of Wildlife Resources conducted a rotenone treatment to remove non-native brook trout during September 2020. The pond was refilled after the treatment.
Project Narrative:
The goal of the project was to remove the non-native trout above the lower dam and create a refuge for this unique combination of native aquatic species (Cutthroat Trout, Northern Leatherside Chub, and Boreal Toad). To facilitate the removal of the non-native Brook Trout, a fish barrier was required to prevent reinvasion of Brook Trout from downstream of the lower dam. The dam was rebuilt to be a full fish passage barrier to Brook Trout and also was improved to modern dam construction procedures. The pond was deepened and expanded to accommodate the consolidation of water rights from the upper pond to the lower pond. Uintalands will use the lower pond for recreational fishing for sterile rainbow trout and wild cutthroat trout.
Future Management:
At least one culvert upstream of the ponds is likely a fish passage barrier. This culvert should be replaced to facilitate fish movement throughout the three miles of stream above the lower pond. The upper pond has some fish passage of its dam and their may be opportunities to further improve fish passage.
Map Features
ID Feature Category Action Treatement/Type
1600 Water development point feature Construction Water Control Structure
1601 Water development point feature Construction Water Control Structure
Project Map
Project Map