Chicken Creek East Boat Ramp (Strawberry Reservoir)
Project ID: 4987
Status: Cancelled
Fiscal Year: 2020
Submitted By: N/A
Project Manager: Alan Ward
PM Agency: Utah Division of Wildlife Resources
PM Office: Central Region
Lead: Utah Division of Wildlife Resources
WRI Region: Central
Description:
The UDWR and the USFS are proposing to build a small watercraft boat launch in the Chicken Creek East Bay (Jakes Bay) of Strawberry Reservoir. The completed project would include road improvements to the site, a paved parking area (which would be accessible year-round), and a hardened boat launch. This proposal would encompass Phase I of the project, and would entail on-site excavation, material purchase and hauling, and grading of the road-way and parking area.
Location:
The project site would be immediately off of Hwy 40 near the current paved Chicken Creek East Parking area on the North end of Strawberry Reservoir, Wasatch County UTM 12T 488208 E 4453949 N.
Project Need
Need For Project:
Strawberry Reservoir is Utah's most important cold water fishery, receiving as much as 1.4 million angler hours on an annual basis. Typically 65% of this pressure is from boat and small watercraft. 65% of all anglers in Utah fish Strawberry on an annual basis. Crowding at access points is often an issue. The entire North end of the reservoir along Hwy 40 is only accessible to small boats and hand-launched water craft at a couple of undeveloped (and risky) launch sites along the old highway roadbed which may be inaccessible under certain water levels. The relatively protected bay at Chicken Creek East provides a great area for small watercraft to fish without having to traverse the often dangerous open water of the main Strawberry Bay. By providing a developed launch in Chicken Creek East, we will provide small craft access to this area, and provide more parking and opportunities during the winter ice fishing season as well. Many angler groups have been asking for improved small craft launch areas to avoid crowding issues at the larger ramps. The current Chicken Creek East parking area does not provide any boat access, and is so far from the water that is often unused by anglers. In addition for the need for more and improved access, there have been many issues with resource damage in critical sage grouse areas near the proposed parking area and boat launch site. Vehicles are often seen continuing along the old highway road bed, and then along the shorelines of the reservoir into areas closed to motor vehicle traffic, and into critical sage grouse habitat. The construction of the new parking area would eliminate the potential for people to access these areas that area already off-limits to motor vehicles.
Objectives:
This fiscal year will encompass engineering. Subsequent phases would provide for excavation, fill, and the installation of the concrete boat ramp, a new outhouse, and for pavement to the roadway and parking area. The old Chicken Creek East parking area would also be reclaimed. The overriding objectives would be to provide improved and safer access for small watercraft on Strawberry in the Chicken Creek East area, improved parking during winter, better disperse traffic at launch sites, and provide protection for sage grouse and other natural resources in the area.
Project Location/Timing Justification (Why Here? Why Now?):
This project would limit motor vehicle traffic from impacting closed areas, and would offer protection for sage grouse in the Strawberry Valley. Damage and impacts are occurring. The current two recreation sites sit in the middle of two large sagebrush communities, whereas the new site is close to the Hwy, part of a smaller sagebrush site and thus less usable by sage grouse. These large sagebrush communities provide sage grouse with important nesting and brood-rearing habitat. Decommissioning the current sites will add approx. 1 acre to quality habitat and reduce habitat fragmentation.
Relation To Management Plan:
The current Strawberry Management plan (UDWR Publication) calls for the support of 1.2 million angler hours of pressure on the reservoir, which we have not met in recent years. Angler perception of crowding has been shown to often limit the desire to fish body of water. By dispersing pressure to a new parking area and small water craft launch site, we can effectively reduce this potential crowding. The current management plan also calls specifically for improvement and development of areas for small water craft launching. The impetus for this comes from the conflicts that often occur between people launching small craft (such as personal inflatable craft, and other small vessels) that require more time to set up and launch than larger boats. The Forest Plan calls for protection of areas for sage grouse, and allows for closure of non-motorized areas to vehicle traffic. Uinta Forest Plan - 2003 Land and Resource Management Plan, Uinta National Forest: https://www.fs.usda.gov/detailfull/uwcnf/landmanagement/planning/?cid=stelprdb5076960&width=full -Plan sites management of riparian areas (pg 2.2), management of aquatic species (pg 2.3), wildlife (pg 2.5), and vegetation (pg 2.5). Rehabilitation Plan for Strawberry Valley Streams 1988 UDWR publication. Identifies the need to rehabilitate valley streams to: 1 increase natural reproduction and 2 enhance water quality. Strawberry reservoir TMDL study 2005. Utah Division of Water Quality publication. Strawberry Watershed Action Plan 2004. USFS publication. Identifies the following for Strawberry River Segment 2A, 2B (SRR Phase IV). This segment needs work to: 1. raise the water table; 2. stabilize stream banks through use of heavy equipment, 3. instream structures, and 4. willow/carex planting. Fish passage is a concern and the segment would be managed as "beaver free" (beaver fencing, relocation etc...). -Utah Mule Deer Statewide Management Plan 2014 The project is designated crucial summer range for Mule Deer. Section IV Statewide management goals and objectives. This project will address Habitat Objective 2: Improve the quality and quantity of vegetation for mule deer on a minimum of 500,000 acres of crucial range by 2013 (p11-12). Strategy F. Encourage land managers to manage portions of pinion-juniper woodlands and aspen/conifer forests in early successional stages. https://wildlife.utah.gov/hunting/biggame/pdf/mule_deer_plan.pdf -Greater Sage-grouse ROD- Attachment C: Utah Plan Amendment GRSG-GEN-DC001-Desired Condition: The landscape for the greater sage-grouse encompasses large contiguous areas of native vegetation, approximately 6-to-62 square miles in an area, to provide for multiple aspects of species life requirements. Within these landscapes, a variety of sagebrush-community compositions exist without invasive species, which have variations in subspecies composition, co-dominant vegetation, shrub cover, herbaceous cover, and stand structure to meet seasonal requirements for food, cover, and nesting for the greater sage-grouse. GRSG-R-GL-064-Guideline: In priority habitat management areas, sagebrush focal areas, and Anthro mtn., new recreational facilities or expansion of existing recreational facilities, including special-use authorizations for facilities and activities, should not be approved unless the development results in a net conservation gain to the greater sage-grouse or its habitat or the development is required for visitor safety. Wasatch County Resource Management Plan encourages land managers to "Maintain, enhance, and expand sport fishing opportunities...". This proposal for the new Chicken Creek East parking area and boat ramp was put before the Wasatch County Council and Public Lands Committee, and they were fully supportive of this effort.
Fire / Fuels:
Construction of this boat ramp will provide an excellent drafting location along the north shore of Strawberry Reservoir. All sized engines and water tenders will be able to directly access the reservoir, reducing drive times to other ramps of difficulties associated with dirt access'. This would have been particularly helpful 2 years ago when 2 small brush fires started along the highway on Strawberry's north shore, one was immediately across Hwy 40 from the new boat ramp site.
Water Quality/Quantity:
Strawberry Reservoir is currently under a TMDL, published and approved in 2005. Reduction of sediment born phosphorus and reductions in oxygen were identified as the loading issues. As part of this project two small perennial streams will be improved to reduce sedimentation. Chicken Creek West flows immediately adjacent to one of the "to be removed" parking areas and access roads. By removing this hardened area sediment currently flowing from the road and parking area will be removed. Another stream, Chicken Creek East flows near the new location of the boat ramp. At sometime in the past this stream was channelized for ~0.4 miles, portions of the stream flow along the Jakes Bay access road, gathering sediment and delivering it to the reservoir. During construction this stream will be moved to a new location where it can function properly. Stream sinuosity will be added and distance from human disturbances will reduce sediment from entering the system and reduce P loading to the reservoir. Overall project design will further reduce loading to Strawberry. By replacing gravel and earthen roads, lots and boat loading areas with asphalt and concrete overland movement of sediment will be removed and dust will not become airborne. Again reducing sediment loading to the reservoir.
Compliance:
The NEPA work for this project was completed during the fall of 2018, and the project is now deemed "shovel-ready".
Methods:
For this phase, the Forest Service engineers will complete the engineering that was started back in 2011 by the UDWR. In subsequent phases, construction crews (either private, or UDWR) will be brought in to excavate material on site and prep the area for material to be brought in. We will then truck in roughly 5,000 CY of material to build up the site in order to level it, and provide adequate slope for the boat ramp installation. This material will be compacted and graded in preparation for subsequent phases where pavement and concrete will be installed. In addition, the existing outhouse approximately 1/4 mile from the site will be moved to a new location at the new parking area.
Monitoring:
UDWR will oversee and monitor all phases of the construction to make sure that the end product will be usable and a benefit to the angling and public. UDWR will also take the lead on making sure that the newly developed site is maintained in good working order to provide this access for years to come. DWR and USFS are currently monitoring sage grouse populations in Strawberry Valley via Radio Telemetry and GPS collars. Usage of reclaimed parking and road areas will be noted and added to the database.
Partners:
The USFS, being the land manager, completed the NEPA for this proposed project during the fall of 2018, and it is critical that we show a good faith effort to uphold our end of the bargain by initiating the construction phase. The USFS is also contributing much of the costs of the engineering by doing the engineering work in-house (with a supplement of $6,000 from the UDWR ), which by so using, greatly reduces the potential for conflicts in engineering designs holding up the process (which can happen with outside engineering). Once the Forest Service engineers complete the work, subsequent phases should be good to go. State Parks may also help contribute in future phases with the 25% match for the Motor Boat Access funds which we are applying for. State Parks also oversee winter plowing efforts to keep these lots open to anglers during the winter months. The Friends of Strawberry Valley have offered $1,000 towards the project. Trout Unlimited has given preliminary pledges for money for the actual boat ramp construction, as well as applying for grants for stream work on the stream that will be moved and restored. And though no money has officially been donated to the project to date, other angler groups have also pledged their support for this project including Sportsman for Fish and Wildlife, Strawberry Anglers Association.
Future Management:
UDWR will take the lead in insuring that structure (asphalt, and concrete) maintenance will be performed, primarily through Motor Boat Access funds. The Forest Service has committed to ensuring that the restroom will be maintained. UDWR, in partnership with State Parks will continue to provide plowing services for winter access for anglers.
Sustainable Uses of Natural Resources:
By providing this access for anglers, we will be insuring that crowding and use at other areas do not overly limit access to Strawberry Reservoir, throughout the entire year. We will also be dispersing certain types of users that have had conflicts at the other boat ramps around the reservoir, thus providing a wider variety of users a more enjoyable and user friendly experience. Reclaimed parking lots will be seeded with native mixes, providing habitat areas for sage grouse, feed for deer and elk and a future grass bank if/when livestock grazing is allowed on Strawberry Project Lands.
Budget WRI/DWR Other Budget Total In-Kind Grand Total
$6,000.00 $44,000.00 $50,000.00 $14,050.00 $64,050.00
Item Description WRI Other In-Kind Year
Contractual Services Engineering of total project $6,000.00 $44,000.00 $0.00 2020
Archaeological Clearance Completed $0.00 $0.00 $7,250.00 2019
NEPA Completed $0.00 $0.00 $6,800.00 2019
Funding WRI/DWR Other Funding Total In-Kind Grand Total
$6,000.00 $44,000.00 $50,000.00 $14,050.00 $64,050.00
Source Phase Description Amount Other In-Kind Year
United States Forest Service (USFS) $0.00 $44,000.00 $0.00 2020
United States Forest Service (USFS) $0.00 $0.00 $14,050.00 2019
Utah Division of Wildlife Resources (UDWR) From Strawberry Current Expense $6,000.00 $0.00 $0.00 2019
Species
Species "N" Rank HIG/F Rank
Bonneville Cutthroat Trout N4 R1
Threat Impact
Channel Downcutting (indirect, unintentional) High
Bonneville Cutthroat Trout N4 R1
Threat Impact
Channelization / Bank Alteration (direct, intentional) High
Bonneville Cutthroat Trout N4 R1
Threat Impact
Increasing Stream Temperatures High
Bonneville Cutthroat Trout N4 R1
Threat Impact
Roads – Transportation Network High
Greater Sage-grouse N3 R1
Threat Impact
Improper Grazing – Livestock (historic) Low
Greater Sage-grouse N3 R1
Threat Impact
OHV Motorized Recreation Low
Greater Sage-grouse N3 R1
Threat Impact
Roads – Transportation Network Low
Kokanee Salmon R3
Threat Impact
Improper Grazing – Livestock (historic) Low
Kokanee Salmon R3
Threat Impact
Increasing stream temperatures High
Habitats
Habitat
Aquatic-Scrub/Shrub
Threat Impact
Channel Downcutting (indirect, unintentional) High
Aquatic-Scrub/Shrub
Threat Impact
Channelization / Bank Alteration (direct, intentional) High
Aquatic-Scrub/Shrub
Threat Impact
Increasing stream temperatures Unknown
Aquatic-Scrub/Shrub
Threat Impact
Roads – Transportation Network Medium
Mountain Sagebrush
Threat Impact
Habitat Shifting and Alteration Medium
Mountain Sagebrush
Threat Impact
Improper Grazing – Livestock (historic) Very High
Mountain Sagebrush
Threat Impact
OHV Motorized Recreation Low
Mountain Sagebrush
Threat Impact
Roads – Transportation Network Medium
Project Comments
Comment 02/14/2019 Type: 1 Commenter: Robert Edgel
Where are you getting seed from to reclaim parking area?
Comment 02/14/2019 Type: 1 Commenter: Alan Ward
Good Question. Based on previous conversations with the Forest Service, restoration of the old parking areas would not occur until the new construction was complete. Therefore, seeding would likely not take place until Phase II, which would be separate from this. However, we may very well need a small amount of seed to take care of some excavated area in Phase I. I will check with the Forest Service to see if they have some on hand, or if we need to add some to our proposal here.
Comment 02/19/2019 Type: 1 Commenter: Justin Robinson
Robbie, I have some seed we can use for any Phase 1 needs. We will work with our Botanist and GBRC for the final reclamation efforts that will happen during Phase 2. Thanks for thinking of seed.
Comment 02/20/2019 Type: 1 Commenter: Justin Robinson
Thanks for all the input during the presentation. I have added the aquatic species you suggested and re-categorized the polygon.
Completion
Start Date:
End Date:
FY Implemented:
Final Methods:
Project Narrative:
Future Management:
Map Features
ID Feature Category Action Treatement/Type
7972 Terrestrial Treatment Area Road decommissioning Road decomissioning
8095 Terrestrial Treatment Area Road/Parking Area Improvements Road/Parking area improvements
Project Map
Project Map