Project ID: 5863
Status: Completed
Fiscal Year: 2022
Submitted By:
18
|
Project Manager: Mark Farmer
PM Agency: Utah Division of Wildlife Resources
PM Office: Central Region
Lead: Utah Division of Wildlife Resources
WRI Region: Central
|
Description:
Install a 1,800 gallon Boss tank guzzler with a metal apron to provide reliable water to wildlife on the Triangle ranch WMA.
|
|
Location:
Triangle Ranch WMA in Juab county
T13S, R1E, section 14
|
Budget | WRI/DWR | Other | Budget Total | In-Kind | Grand Total |
$0.00 | $6,000.00 | $6,000.00 | $3,000.00 | $9,000.00 |
Item | Description | WRI | Other | In-Kind | Year |
---|---|---|---|---|---|
Materials and Supplies | 1,800 gallon Boss tank guzzler | $0.00 | $6,000.00 | $0.00 | 2022 |
Materials and Supplies | Materials to build a metal apron and livestock exclusion fence | $0.00 | $0.00 | $2,500.00 | 2022 |
Personal Services (permanent employee) | Permanent employee time to install guzzler tank, apron and fence | $0.00 | $0.00 | $500.00 | 2022 |
Funding | WRI/DWR | Other | Funding Total | In-Kind | Grand Total |
$6,000.00 | $0.00 | $6,000.00 | $3,246.69 | $9,246.69 |
Source | Phase | Description | Amount | Other | In-Kind | Year |
---|---|---|---|---|---|---|
Utah Division of Wildlife Resources (UDWR) | Money from the CRO WMA maintenance budget for apron and fence materials | $0.00 | $0.00 | $2,500.00 | 2022 | |
National Wild Turkey Federation (NWTF) | S024 | Project approval coversheet indicated this was direct pay, however the funds were sent to DWR. | $6,000.00 | $0.00 | $0.00 | 2022 |
Utah Division of Wildlife Resources (UDWR) | In-kind labor by permanent employees and use of Regional backhoe | $0.00 | $0.00 | $500.00 | 2022 | |
DWR-WRI Project Admin In-Kind | $0.00 | $0.00 | $246.69 | 2022 |
Species | "N" Rank | HIG/F Rank | ||||
---|---|---|---|---|---|---|
Chukar | R3 | |||||
|
||||||
Elk | R2 | |||||
|
||||||
Wild Turkey | R1 | |||||
|
||||||
Mule Deer | R1 | |||||
|
Habitat |
---|
Comment | 10/21/2021 | Type: 2 | Commenter: Alison Whittaker |
Hey Guys! Is this project going to happen this fiscal year? If so make sure that a project approval coversheet is filled out and signed by NWTF, Eric, Justin and the DO's office before you move ahead with using conservation permit funds. If you need more info on this let me know and I will send you the form and the instructions. If your plans have changed let me know so I can move it to cancelled for the time being. Thanks. | |||
Comment | 08/22/2022 | Type: 2 | Commenter: Alison Whittaker |
Please enter the missing expenses, highlighted in rust, on the Finance Page. With this being a project where NWTF purchased the guzzler directly please work with them to get a copy of the receipt or cleared check that shows the amount that they paid and upload a copy to the images and documents tab. When you have completed that, please go back to the Completion Form and finalize your report again so I know that it has been completed. Thanks. | |||
Comment | 08/23/2022 | Type: 2 | Commenter: Alison Whittaker |
Mark - Thanks for the additional info on the program number to remind me that they actually didn't do direct pay. I fixed it on the finance page to show that those funds went through WRI/DWR and not other. Sorry to make you add an invoice that wasn't needed. I moved the project to completed. |