UKC-Spencer Bench
Region: Southern
ID: 5281
Project Status: Completed
Map This Project
Export Project Data
Completion Form
*
Project Start Date
*
Project End Date
Fiscal Year Completed
2021
*
Final Methods
Project was flagged and layed out by BLM personnel. Arch clearance was contracted through state contracting and coordinated through the BLM archeologist. 1,809 acres aerial seeded on November 16th 2020 with a mix of grasses, forbs, and shrubs. 1,640 acres two way Ely chained Beginning December 16th,2020 finishing March 17th, 2021. 169 acres Mechanical mulched beginning March 25th, 2021 completed on April 9th, 2021. Due to un availability of forage kochia seed no second seed flight took place.
*
Project Narrative
Project was flagged and layed out by BLM personnel. Aerial seeding contract started on November 16th 2020, it was completed in one day. A total of 1,809 acres were seeded with a mix of grasses, forbs, and shrubs with a fix wing aircraft contracted by Hammond Helicopters. Seed was consistent throughout the project area and contractor did a good job ensuring stipulations were met. Due to un availability of forage kochia seed no second seed flight took place. 1,640 acres were two way Ely chained, Chaining began on December 16th using two D8 dozers rented from Wheeler Machinery through a state contract. Dozers were operated by BLM personnel and fuel for dozers was coordinated by Curtis Roundy with the state DNR. Ely chains were coordinated and delivered by Ron Larson with the state DNR. On February 18th, 2021 two additional dozers were brought in to help with the chaining. The Chaining was complete on March 17th, 2021. Portions of the arch sites with in the project were mulched to meet project needs and archeologist desires. Mechanical mulching began on March 25th, 2021. Brushwacker inc. was awarded the contract and they completed mastication treatments on April 9th, 2021 for a total of 169 acres. Overall the project area looked good and met all contract stipulations and specifications.
*
Future Management
Project area will be monitored for vegetative trend, cover and wildlife use for the next 3 years. The project area will be rested from livestock for a minimum of 2 complete growing seasons in order to allow the seedlings to become established and set seed. This rest period may be extended if monitoring shows the seeding has not sufficiently established. Kanab Field Office BLM will then begin reading trend on a 5 year interval and utilization data will be collected on an annual basis. Maintenance of the project will be completed in the future by lop and scatter projects
Submitted By
John Reese