  • Goose Creek Fire Stream Restoration - Phase 2
  • Region: Northern
  • ID: 5301
Project Status: Completed

Comments

Admin

  • Alison Whittaker
    Aug 19, 2021, 1:52:36 PM
    This is just a reminder that completion reports are due August 31st. I have entered the expenses in the Through WRI/DWR column on the finance page. Please do not make any changes to numbers in the Through WRI/DWR column. Any "Through Other" or "In-kind" expenses will need to be entered by the PM or contributors. Update your map features and fill out the completion form. Be sure to click on the finalize button on the completion report when you have your completion report ready to be reviewed by WRI Admin. Don't forget to upload any pictures of the project you have of before, during and after completion. If you have any questions about this don't hesitate to contact me. Thanks.
  • Alison Whittaker
    Aug 25, 2021, 11:29:21 AM
    Thank you for submitting your completion form on time. It looks great. Thanks for uploading pictures!

Project

  • Jimi Gragg
    Jan 30, 2020, 1:44:00 PM
    I strongly suspect you will improve habitat for lots of other wildlife species. Talk with some biologists to get ideas? Bats, songbirds, frogs and toads. Heck, mule deer. Good luck!
  • Ethan Hallows
    Jan 30, 2020, 4:28:00 PM
    We will do that. Thanks for the suggestion.

Financial

  • Alison Whittaker
    Sep 14, 2020, 6:51:15 PM
    Who will be providing the labor for the in-kind work?
  • Ethan Hallows
    Sep 15, 2020, 12:07:36 PM
    SITLA will be doing the labor.